Published 10 Jul 2019 - 12.27
Environment and Nature
Press release of 10/07/2019 of the Municipality of Asiago
In reference to the asbestos clean-up work in the area affected by the underground park in Via Trento and Trieste in Asiago it is announced that the next works will have the following chronoprogram:
- on 09/07/2019, the last checks were carried out by Arpav ofVicenza;
- in the week of 15/07/2019, technical and visual checks of the dislocated material will take place and the excavation fund of the remediation area will be tested;
- later towards the end of July and in relation to the results of the excavation background test, which will decree the end of the asbestos remediation, in-depth excavations relating to the construction of the parking lot can begin underground and ancillary works;
- in September, the castings of the parking lot's foundation audience and the continuation of subsequent work can begin.
It should be noted that the programme time described may have changes as a result of adverse weather conditions